Do you need a health and safety project supervisor for a home fit-out?
S.L. 646.27 makes the client — that is you, the property owner — responsible for appointing a health and safety project supervisor from OHSA's register, in writing, before any work starts. Finishing works are explicitly covered, and the exemption for domestic clients is narrower than most people assume.

Most people buying in Malta buy a shell: bare blockwork, a screed if you are lucky, services stubbed to a wall. Finishing it feels like a domestic matter — a few trades, a few months, your own flat. Since 7 September 2025 the law has taken a different view. Under the Health and Safety at Work (Minimum Health and Safety Requirements for Work at Construction Sites) Regulations, S.L. 646.27 (L.N. 52 of 2025), the client — the owner — must appoint a project supervisor for health and safety before works begin, and for a multi-trade fit-out the exemptions usually do not apply.
These regulations replaced S.L. 646.25 and implement Directive 92/57/EEC, so the structure will be familiar if you have built in another EU member state. What is new in Malta is that the "competent person" is now tied to a formal OHSA register rather than being a matter of judgement.
Finishing works are inside the scope
The common assumption is that "construction site" means a crane, a hoarding and a hole in the ground. The regulations do not read that way.
Regulation 2 defines a project as running to completion including finishing works. Schedule I, which sets out the works covered, lists fitting-out, alterations, renovation, maintenance and painting. An apartment being taken from shell to habitable is squarely within that. So is a renovation of an older townhouse, and so is a repaint-and-replumb job that would barely register as a project in conversation.
The other definition that matters is contractor, which includes self-employed persons. In the Maltese market, where the electrician, the plumber, the tiler, the aluminium installer and the gypsum crew are often individually self-employed and individually engaged, that definition does a lot of work.
What the client has to do
Regulation 3 puts the duty on the client, not the builder.
- Appoint a project supervisor for health and safety chosen from OHSA's competent persons register (reg. 3(1)).
- You may appoint yourself only if you are personally registered as competent (reg. 3(2)). Being an experienced property investor does not qualify you.
- The engagement must be in writing (reg. 3(3)).
- Work may not start or progress until the appointment has been made and notified to OHSA (reg. 3(4)).
- If the supervisor dies or the engagement is terminated, OHSA must be notified within 15 days, and work stops until a replacement is appointed (regs. 3(5)–(7)).
Starting without a project supervisor is an offence under regulation 3(8).
Three further client duties sit alongside the appointment:
- Regulation 4 — the client keeps a health and safety file for the works and hands it over to any buyer. If you sell the property later, the file goes with it.
- Regulation 5 — a health and safety plan must exist before the site is set up, not once the trades are already in.
- Regulation 6 — prior notice to OHSA at least four calendar weeks before works begin, where the job will last more than 30 working days and have more than 20 workers on site simultaneously, or where it exceeds 500 person-days. A copy of that notice is displayed on site. Most single-dwelling fit-outs will not reach these thresholds; a large villa or a whole-block renovation might.
Regulation 10 is worth reading twice: appointing a project supervisor does not relieve the client of responsibility. You delegate the function, not the liability.
The domestic client exemption, and why it is narrow
Regulation 8 disapplies regulation 3 for a domestic client — but only where all three of the following hold:
- (a) no prior notice under regulation 6 is required;
- (b) only one contractor is present for the whole project;
- (c) none of the Schedule II risks arise.
A "domestic client" is defined in regulation 2 as someone having minor works done, not for the purposes of a business, in premises they own or lawfully occupy. Note the word minor. A full shell-to-finish fit-out is not obviously minor work, and the definition gives no square-metre or value threshold to measure against.
Condition (a) is usually satisfied for a single flat. Condition (b) is where most fit-outs fail. If you engage your own electrician, your own plumber, your own tiler and your own gypsum installer, you have four contractors on the project, because self-employed persons count. Condition (c) catches more jobs than people expect: Schedule II includes falls from height where the risk is aggravated by the nature of the work, work with dangerous chemical or biological substances, work near high-voltage power lines, and assembly of heavy prefabricated components. Waterproofing a roof, installing façade apertures from a scaffold, or craning in a prefabricated element will each want checking against that list.
What the regulations do not settle is whether a single main contractor using its own subcontractors counts as "one contractor" for the purposes of (b). That is the question that decides the exemption for a turnkey arrangement, and the text does not answer it. Confirm it with OHSA rather than assuming either way.
What the project supervisor actually does
The supervisor is not a box-ticking signature. Under the new regime they can receive health and safety concerns from any interested party — which in a Maltese apartment block means neighbours and the condominium can raise matters with a named person — and they can inspect the site and order works halted where there is reasonable concern of serious risk. Contractors, including self-employed ones, must follow the supervisor's directions, implement the health and safety plan and keep written risk assessments.
For an owner living abroad while a Gozo or Sliema fit-out proceeds, that halt power is a real factor in programme risk. It is also, read the other way, the only on-site authority that exists independently of the people you are paying.
Appointing a client representative
Regulation 9 allows the client to appoint a representative who takes on the client's duties. The representative must be resident or established in the EU or EEA and must be notified to OHSA with the prescribed details. A turnkey contractor managing the whole fit-out can be appointed in this role, which is how most non-resident owners will deal with the practicalities. Regulation 9 was among the provisions touched by L.N. 109 of 2026, and we have not compared the amended wording line by line, so check the current consolidated text on legislation.mt before relying on the detail.
Again: regulation 10 means this does not make you no longer the client.
Finding a supervisor
OHSA maintains the competent persons register at ohsa.mt/competent. The page carries a downloadable register PDF, an eForm for persons applying to be listed, the initial-application-fee document, and the underlying Administrative Instrument No. 1 of 2025 in English and Maltese, made under article 17 of the Health and Safety at Work Act (Cap. 646). OHSA can be reached at ohsa@ohsa.mt or on 138.
Two practical points. First, the register is a list of people entitled to act, not a price list — no market rates for residential project supervision appear to be published anywhere. Second, the appointment has to be made and notified before works start, so this belongs in your pre-contract sequence alongside the Planning Authority position and condominium consents, not in the week the scaffold arrives.
This article summarises published regulations and is not legal advice. Verify the current text of S.L. 646.27 on legislation.mt and confirm your own position with OHSA or a lawyer.
Common questions
- Is a fit-out really a 'construction site' under Maltese law?
- Yes, in most cases. Regulation 2 of S.L. 646.27 defines a project as running to completion 'including finishing works', and Schedule I lists fitting-out, alterations, renovation, maintenance and painting among the works covered. A shell apartment being finished is within scope.
- I am a private owner doing up my own flat. Doesn't the domestic client exemption cover me?
- Only if all three conditions in regulation 8 are met at once: no prior notice to OHSA is required, only one contractor is present for the whole project, and none of the Schedule II risks arise. A typical fit-out with a separate electrician, plumber, tiler and gypsum installer fails the single-contractor test, because 'contractor' includes self-employed persons.
- Can my turnkey contractor handle this for me?
- Regulation 9 allows you to appoint a client representative, who must be resident or established in the EU or EEA and must be notified to OHSA with the prescribed details. That representative takes on the client's duties. It does not, however, remove your own position as client under regulation 10, and the supervisor must still come from OHSA's competent persons register.
- What happens if I just start the works without appointing anyone?
- Regulation 3(4) says work may not start or progress until the appointment is made and notified to OHSA, and regulation 3(8) makes starting without a project supervisor an offence. We have not loaded the penalty provisions, which sit in the Health and Safety at Work Act (Cap. 646), so we cannot state the amounts.
- Where do I find a project supervisor?
- OHSA publishes a competent persons register on its website at ohsa.mt/competent, with a downloadable PDF of listed persons. The register was set up under Administrative Instrument No. 1 of 2025, linked to article 17 of Cap. 646. OHSA can be contacted at ohsa@ohsa.mt or on 138.
What we could not establish
- Whether a turnkey main contractor using its own subcontractors counts as 'one contractor' for the purposes of regulation 8(b) is not defined in the regulations. This is the single most important open question for a typical fit-out and should be confirmed with OHSA before relying on the exemption.
- S.L. 646.27 was amended by L.N. 109 of 2026, which touched the regulation 2 definitions and regulation 9. We have not compared those amendments line by line against the original text.
- Penalty amounts for the offence under regulation 3(8) sit in the Health and Safety at Work Act (Cap. 646) and were not consulted.
- OHSA's fees, if any, for the project supervisor notification are not established. The only fee document seen on the competent persons page is an initial-application fee for persons applying to be listed on the register.
- No market data was found on what project supervisors charge for residential fit-outs in Malta. Nobody appears to publish this.
Sources
- Health and Safety at Work (Minimum Health and Safety Requirements for Work at Construction Sites) Regulations (S.L. 646.27) — Government of Malta / legislation.mt · read 2026-10-26
- Competent Persons Register — Occupational Health and Safety Authority (OHSA) · read 2026-10-26
- New construction site regulations now in force in Malta — MAMO TCV Advocates · read 2026-10-26
Drafted with Claude — claude-opus-5, then read, corrected and approved by Neil Bennett before publication. We do not publish anything a person has not read.