What the calculator's number includes, and what it leaves out
The calculator produces a budget, not an offer. This sets out the trades inside the number, the items the rate card leaves unpriced, and the known gaps — including the absence of any Gozo uplift.

A budget calculator is only useful if you know where its edges are. A number with undefined edges is worse than no number, because you will plan around it, negotiate a purchase price against it, and then discover the gap at the worst possible moment — after completion, when the shell is yours and the money is spent.
So: here is what the turnkey.mt calculator's figure contains, what it deliberately does not, and the point at which it stops being a budget and has to become a quote.
What a shell actually is
Most property in Malta is sold in shell form, and this surprises buyers coming from the UK or elsewhere in the EU, where a flat usually changes hands with a kitchen in it. Here, a shell is structure and envelope. The frame is up, the external walls are built, the apertures may be holes. Everything that makes it habitable — partitions, plaster, screeds, first and second fix electrical and plumbing, tiling and flooring, apertures, joinery, decoration — has not happened yet and is your cost.
The calculator exists because that cost is invisible to someone reading a property listing. It groups the finishing work into ten shell trades and applies published rates to the areas you enter.
What sits inside the number
The ten shell trades. These are the core of the figure. Every calculation includes them, because they are not optional: a shell cannot become a home without each one happening. They are the trades that take you from bare blockwork and concrete to a finished, serviced, decorated interior.
Kitchen. Priced as its own line, not folded into the shell trades, because the range of what people spend on a kitchen is wide enough that burying it inside a square-metre rate would distort everything around it.
Bathrooms. Likewise separate, and counted — the number of bathrooms drives the figure, because each one is a concentration of plumbing, waterproofing, tiling and fittings in a small area.
Pool. Included where you select it. If you do not select it, nothing in the figure is doing pool work.
Villa external works. Included where selected. This is the layer that apartment owners do not have and villa owners cannot avoid: the works outside the building envelope that still have to be paid for by somebody.
The rule is simple. Shell trades are always in. Kitchen, bathrooms, pool and villa external works are in when you have selected them. If you did not tick it, it is not in your number.
What sits outside the number
The noPublishedRate list
The rate card contains a category it calls `noPublishedRate` — items it names but refuses to price. This is deliberate and it is the most honest thing in the calculator. Some work varies so much between one property and the next that a published square-metre rate would be a fiction: it would produce a confident-looking number that is wrong in both directions depending on the building.
These items are listed so that you know they exist and can ask about them. They are not in your total. If your project involves one of them, your real cost is the calculator figure plus something the calculator has not told you.
Permits and perit fees
Outside. The Planning Authority governs what you may do to a building in Malta, and the professional layer — the perit who signs off on work — sits alongside the trades rather than inside them. Neither appears in the rate card. Both are real money and both come before, not after, the building work.
Anything structural
Outside. Moving a load-bearing element, altering the frame, opening up a floor slab — none of that is priced by a finishing rate card, and it should not be. Structural work is a different discipline with a different risk profile and a perit's involvement is not optional.
Furniture and everything soft
Outside. The figure delivers a finished property, not a furnished one. Sofas, beds, wardrobes that are not fitted joinery, curtains, appliances that are not part of the kitchen line — none of it is in there. Buyers consistently underestimate this layer because they think of it as shopping rather than as project cost, and then find they have a finished apartment they cannot live in yet.
Condominium constraints
If you are finishing an apartment, the condominium rules bind you: what you may do to common parts, when you may make noise, how materials get up the building. These do not appear as a line in the rate card, but they shape sequencing and access, and sequencing is cost.
The Gozo gap
The rate card carries no Gozo uplift. None. The same rates apply whether the property is in Msida or in Nadur.
Every material delivery to Gozo crosses on a ferry. Every load of tiles, every pallet of blocks, every kitchen, every van carrying two men and their tools. That crossing has a cost in money and in time, and the published rates do not reflect it.
We know about this. It is not an oversight we are hoping you will not notice — it is stated here because an article about the edges of a number that hid its largest edge would be pointless. If your property is in Gozo, the calculator will give you a figure that is too low, and no source we can point you at establishes by how much. Ask for it to be priced specifically.
Where the budget stops and the quote starts
The calculator is a screening tool. Its job is to tell you, before you commit to a purchase, roughly what finishing this property will cost — well enough to decide whether the asking price plus the finishing makes sense against your budget.
It stops being adequate at the point where any of the following is true:
- You have signed, or are about to sign, a promise of sale.
- Your project touches anything on the `noPublishedRate` list.
- The property is in Gozo.
- Anything structural is in scope.
- You need to know the number to within a few per cent rather than approximately.
From that point you need a measured, site-visited quote against the actual shell — because the calculator has never seen your ceiling heights, your aperture openings, the state of your screeds, or how a van gets to your door.
A short checklist for reading your own figure
- Did I select the kitchen, bathroom count, pool and villa external works that my project actually has?
- Have I read the `noPublishedRate` list and checked whether any of it applies to me?
- Have I put a separate line in my own budget for permits and perit fees?
- Have I put a separate line in for furniture and appliances?
- Is anything I want to do structural?
- Is the property in Gozo — and if so, have I flagged that the figure does not account for the crossing?
If you can answer all six, the number in front of you is doing what it was built to do. If you cannot, the number is still a number, but it is not yet yours.
Common questions
- Is the calculator's number a quote?
- No. It is a budget built from a published rate card applied to the areas and options you enter. It becomes a quote only after someone has measured the property, seen the actual shell, and priced the items the rate card leaves unpriced. Treat the calculator figure as the number you use to decide whether a property is worth pursuing, not the number you sign.
- Does the rate card add anything for a property in Gozo?
- No. There is no Gozo uplift anywhere in the rate card, even though every material delivery to Gozo crosses on a ferry. The same rates are applied whether the property is in Sliema or Xagħra. That is a known gap, and a Gozo budget taken straight from the calculator will sit below what the job actually costs by an amount the rate card does not state.
- Are Planning Authority permits and perit fees inside the number?
- No. Permits and perit fees are outside the calculator entirely. The rate card prices construction trades; it does not price the statutory and professional layer that sits around them. Budget for those separately, and find out early whether your works need a Planning Authority permit at all.
- What does noPublishedRate mean?
- It is the rate card's own label for items it will not put a number against — work that varies too much from property to property for a published square-metre rate to mean anything. Those items are named in the calculator so you know they exist, but they are not costed, and nothing in your figure covers them.
What we could not establish
- The rate card carries no Gozo uplift, and no source establishes what the ferry crossing adds to a Gozo project — neither a percentage nor a per-delivery figure exists in the published rates.
- This article does not reproduce the per-trade figures; the calculator itself is the live version and should be read directly for current rates.
- The rate card states that its figures exclude VAT, which Malta charges at 18% on top. It does not break them down into labour and materials.
- No source establishes how long a given rate is valid for, or how it is revised.
- No published figure exists for Planning Authority permit costs or perit fees on a Maltese finishing project.
- The rate card does not establish a price for structural work, because structural work is outside it entirely.
Sources
- Turnkey.mt budget calculator rate card (js/main.js) — Turnkey.mt · read 2026-09-02
Drafted with Claude — claude-opus-5, then read, corrected and approved by Neil Bennett before publication. We do not publish anything a person has not read.